VI
EN

ASME B31.3 Preheat for Process Piping — P-Number Classification, Practical Guide & Tempilstik® Selection

ASME B31.3 Process Piping governs the majority of piping installation work in refineries, gas plants, chemical plants, and industrial processing facilities in Vietnam. Unlike AWS D1.1 — which classifies steel by Carbon Equivalent and wall thickness — ASME B31.3 classifies materials by P-Number, ASME's own grouping system based on chemical composition and mechanical properties. Understanding P-Number and its corresponding preheat requirements is a fundamental competency for welding engineers, welding inspectors, and QA/QC personnel in process piping work.

Measuring preheat temperature on process piping using Tempilstik temperature indicating crayon at an industrial construction site
Each P-Number in ASME B31.3 carries different preheat requirements. Selecting the correct Tempilstik® part number by P-Number and wall thickness is essential for code-compliant preheat verification.

ASME B31.1 vs ASME B31.3 — Key Differences

These two codes are frequently confused, especially on projects that combine power generation with industrial processing systems:

Criterion ASME B31.1 — Power Piping ASME B31.3 — Process Piping
Scope Power plants: main steam lines, steam extraction, boiler feedwater Refineries, chemical plants, gas processing, LNG, industrial process systems
Inspection authority Authorized Inspector (AI) per B31.1 Owner's Inspector per B31.3
PWHT requirements More stringent — mandatory PWHT at lower wall thicknesses Higher thickness thresholds before PWHT is triggered
Typical applications in Vietnam Steam turbine piping, power plant boiler systems BSR (Dung Quat Refinery), PVFCCo, GPP gas processing plants
P-Number system Identical — governed by ASME Section IX

P-Number System in ASME B31.3

The P-Number is ASME Section IX's material grouping number — the foundation for developing WPS documents and determining preheat and PWHT requirements. The following table covers the P-Numbers most commonly encountered in process piping in Vietnam:

P-Number Material Group Typical Grade Min Preheat (B31.3) Tempilstik® Part No.
P-No.1 Carbon steel A106 Gr.B, A53 Gr.B, API 5L Gr.B 10°C (t < 25 mm) / 79°C (t ≥ 25 mm) #28009 (175°F / 79°C)
P-No.1 (heavier section) Higher-carbon grade A106 Gr.C, heavy wall 79°C / 121°C #28009 / #28019
P-No.3 Low-alloy (0.5Mo) A335 P1, A161 T1 79°C (175°F) #28009
P-No.4 Low Cr-Mo (1.25Cr-0.5Mo) A335 P11, A213 T11 150°C (302°F) #28318
P-No.5A Medium Cr-Mo (2.25–3Cr) A335 P22, A335 P21 200°C (392°F) #28327
P-No.5B High Cr-Mo incl. P91 (5–9Cr) A335 P91, A335 P9 200°C (392°F) #28327
P-No.8 Austenitic stainless steel A312 TP304, TP316, TP321 No preheat required
Note: The values above are reference figures from ASME B31.3 Table 330.1.1. Actual preheat requirements depend on the specific wall thickness, chemical composition from the Mill Test Certificate, and welding conditions. Always verify against the code original and the approved WPS. For a comprehensive lookup table see the preheat temperature reference table.

Case Study: Welding A106 Gr.B 6-inch Schedule 80 Pipe to a Class 600 Flange

This is one of the most common field situations in process piping — welding a pipe to a flange that is substantially thicker than the pipe wall. Preheat determination is more complex because the two components have significantly different wall thicknesses.

Component specifications

ComponentMaterialStandardThickness at weld
Pipe ASTM A106 Gr.B — DN 6" (168.3 mm OD) Sch.80 P-No.1 10.97 mm
Flange ASTM A105 — Class 600 — DN 6" (hub at weld bevel) P-No.1 ~38 mm

Step-by-step preheat determination

  1. Confirm P-Number: Both A106 Gr.B (pipe) and A105 (flange) are P-No.1 (carbon steel). WPS: P-No.1 to P-No.1.
  2. Determine governing thickness: Per ASME B31.3, when the two components have different thicknesses, preheat is determined by the greater thickness at the weld joint. The Class 600 DN 6" flange hub at the bevel is approximately 38 mm.
  3. Apply Table 330.1.1: P-No.1 with t ≥ 25 mm → minimum preheat 79°C (175°F).
  4. Select Tempilstik®: Part #28009 (175°F / 79°C).

Field measurement sequence

  1. Heat the full pipe circumference and flange hub using resistance heating wire or propane torch.
  2. Mark Tempilstik® #28009 at positions at least 75 mm from the weld bevel on the pipe side — at 4 evenly distributed points (0°, 90°, 180°, 270°).
  3. Also mark the flange hub face — the thickest point, farthest from the heat source, slowest to reach temperature.
  4. Begin welding only when all measurement points show the crayon has melted — confirming uniform preheat across the full joint.
  5. Document in the Preheat Record (ITR): time, temperature, measurement method (Tempilstik® #28009), measurement locations, inspector name.
Interpass temperature for P-No.1: With P-No.1 carbon steel, maximum interpass temperature per most WPS is 250–300°C. If the WPS specifies interpass ≤ 250°C, use Part #28039 (450°F / 232°C) as the interpass check — when #28039 has not melted, the surface is below 232°C and safely within the 250°C limit.
Tempilstik crayon being applied to pipe surface to verify preheat temperature before welding per ASME B31.3
Applying Tempilstik® to confirm preheat on a pipe-to-flange weld — mark at the flange hub as well as the pipe, since the hub is the thickest section and the last to reach temperature.

PWHT Requirements per ASME B31.3

ASME B31.3 defines wall thickness thresholds above which PWHT becomes mandatory for each P-Number. This is the second most important parameter after preheat:

P-Number Wall Thickness Requiring PWHT (B31.3) PWHT Temperature Tempilstik® Spot-Check
P-No.1 t > 19 mm (¾") 595–650°C (1103–1202°F) #28047 (316°C) — heating phase checkpoint
P-No.4 All thicknesses 675–760°C (1247–1400°F) #28057 (550°C)
P-No.5A All thicknesses 675–760°C (1247–1400°F) #28057 (550°C)
P-No.5B (P91) All thicknesses — no exceptions 730–760°C (1346–1400°F) #28065 (788°C)
P-No.8 Not applicable

For full PWHT procedure details, soaking time requirements, and the role of Tempilstik® in heat treatment verification, see PWHT — Post Weld Heat Treatment.

Frequently Asked Questions

Per ASME B31.3 Table 330.1.1, P-No.1 with wall thickness under 25 mm requires a minimum preheat of 10°C — in practice, confirming the surface is free of moisture and above 10°C. In Vietnam's climate, this is generally met naturally, but must still be documented. Some stricter WPS documents require 50–79°C even for thin-wall pipe to fully eliminate moisture.

The greater of the two thicknesses at the weld joint governs — not an average. This conservative rule ensures the thicker component, which is more prone to residual stress accumulation, receives adequate preheat. For Sch.80 pipe (10.97 mm) welded to a Class 600 flange hub (~38 mm), preheat is governed by the 38 mm hub dimension.

Temperature at the bevel face reflects the instantaneous surface temperature — not the through-thickness heat penetration. Measuring 75 mm from the weld edge confirms that the metal which will become the HAZ has also reached the required temperature, not just the surface exposed directly to the heat source.

ASME B31.3 does not prescribe a specific preheat record format, but the Owner's Inspector has the right to request evidence of WPS compliance. In practice on O&G and EPC projects in Vietnam, a Preheat Record in ITR format is mandatory — documenting time, temperature measured, measurement method (Tempilstik® part number), measurement location, and inspector name.

Need Tempilstik® for ASME B31.3 process piping projects?

Fast Group Engineering — authorized Tempil® distributor in Vietnam. Free P-Number to part number consultation. C/O + C/Q + VAT invoice. Stock in HCMC and Vung Tau.

📞 +84 938 888 958  |  ✉ sales@tempil.vn

Related Articles