VI
EN

P91 Steel Welding — Preheat 200°C, Interpass ≤300°C & Mandatory PWHT 730–760°C

P91 steel — full designation ASME SA-335 Grade P91, composition 9% Chromium – 1% Molybdenum – Vanadium — is a creep-resistant alloy used in main steam lines, hot reheat piping, and headers in thermal power plants, as well as in high-pressure process piping in refineries. Its tempered martensite microstructure with finely dispersed carbides enables service at up to 600–625°C under high pressure. That same microstructure makes P91 one of the most demanding steels to weld and one of the most unforgiving of temperature control errors on site.

Tempilstik temperature indicating crayon used on P91 alloy steel pipe to verify preheat temperature before welding
P91 pipe welding requires minimum preheat 200°C and maximum interpass 300°C. Tempilstik® confirms the surface has reached the required threshold before each weld pass.

Why P91 is More Difficult to Weld Than Carbon Steel

During welding, the heat-affected zone (HAZ) and weld metal of P91 undergo a complex phase transformation sequence. As the joint heats and cools, the austenite structure transforms to martensite — a hard, brittle phase. The critical transformation temperatures for P91 are:

This means the joint must be cooled below 200°C — close to ambient temperature — before PWHT is applied. The weld cannot be taken directly from the welding temperature into the PWHT furnace.

Common error by engineers less familiar with P91: Some deliberately hold the joint at elevated temperature after welding to "avoid thermal shock," believing this is protective. In practice, preventing the joint from cooling below Mf stops the martensite transformation from completing — and PWHT applied to a joint that still contains untransformed austenite will not achieve the required stress relief or tempering effect. The resulting weld has retained unstable austenite and will not meet code mechanical property requirements.
⚠️ Technical warning: For P91, PWHT is not optional — it is a mandatory requirement under ASME B31.1, ASME B31.3, and EN 1011-2. Omitting PWHT or executing it below the specified temperature or duration leaves residual stress and un-tempered martensite in the HAZ, creating direct conditions for creep failure after thousands of hours in high-temperature service.

Three Mandatory Temperature Parameters for P91 Welding

1. Minimum Preheat: 200°C (392°F)

ASME B31.1 and B31.3 require a minimum preheat of 200°C (392°F) for P91 (P-Number 5B). The purpose of preheat for P91 is not only to prevent hydrogen-induced cold cracking — it is also to reduce the thermal gradient between the weld zone and the surrounding base metal, which is especially important because P91 has lower thermal conductivity than plain carbon steel.

Tempilstik® part number for preheat verification: #28327 (392°F / 200°C).
Measure at a minimum of 4 evenly distributed points around the full pipe circumference, at least 75 mm from the weld edge on each side. A single-point check is not acceptable.

2. Maximum Interpass Temperature: 300°C (572°F)

While preheat is a minimum threshold, interpass temperature is a maximum limit that must not be exceeded. For P91, the standard maximum interpass temperature is ≤ 300°C (572°F).

If the surface temperature in the weld zone exceeds this limit before depositing the next pass, welding must stop and the joint must be allowed to cool. Excessive interpass temperature causes austenite grain coarsening in the HAZ, reducing Charpy impact toughness — P91 welds in main steam systems must meet strict impact energy requirements per ASME.

Tempilstik® for interpass maximum check: #28047 (600°F / 316°C).
This crayon melts at 316°C. If it liquefies on contact, the surface has exceeded 300°C — stop welding, allow natural cooling, re-measure before continuing.

Two-crayon field technique for P91: Mark #28327 (preheat minimum) before each pass — must be melted before welding begins. Mark #28047 (interpass maximum guard) before each subsequent pass — must not be melted. Both conditions must be satisfied simultaneously.

3. Cool Below 200°C Before PWHT, Then PWHT at 730–760°C (1350–1400°F)

After the weld is complete and the joint has cooled below 200°C (to allow complete martensite transformation), PWHT must be performed in the range 730–760°C (1350–1400°F). Minimum soaking time per ASME: 1 hour per 25 mm of wall thickness, minimum 1 hour regardless of thickness.

PWHT is performed using electric resistance heating or a furnace, with thermocouples continuously recording temperature via a data logger. Tempilstik® is used for supplementary spot-check confirmation at locations not directly covered by thermocouples:

Tempilstik® supplements the thermocouple record — it does not replace it. The thermocouple data logger is the mandatory primary QA document for PWHT.

Temperature indicator confirming PWHT temperature has been reached on P91 pipe weld
Tempilabel® Series 21 applied directly to P91 pipe — records the maximum temperature reached during the PWHT cycle as supplementary visual evidence in the QA record.

Summary Table — P91 Temperature Requirements & Part Numbers

Stage Requirement Temperature Tempilstik® Part No. Applicable Standard
Preheat Minimum 200°C / 392°F #28327 ASME B31.1, B31.3
Interpass Maximum — must not exceed 300°C / 572°F #28047 (melts at 316°C) ASME B31.1, B31.3, EN 1011-2
Pre-PWHT cool-down Must reach below this point < 200°C / 392°F #28327 (used as indicator) Metallurgical requirement
PWHT — lower bound Minimum soak temperature 730°C / 1346°F #28065 (788°C spot-check) ASME B31.1 Table 132
PWHT — upper bound Maximum — must not exceed 760°C / 1400°F Thermocouple data logger ASME B31.1 Table 132

Consequences of Non-Compliance — Documented Cases

Creep failure in P91 welds is a well-documented failure mode that has occurred at multiple power plants worldwide, particularly from the early 2000s when P91 adoption expanded rapidly but welding and PWHT procedures were not yet fully standardized. Failure typically initiates at the CG-HAZ (Coarse Grain HAZ) and FG-HAZ (Fine Grain HAZ) — zones that develop a weak "Type IV" microstructure when PWHT is performed below the minimum temperature or for insufficient duration.

Documented contributing factors to premature P91 creep failure:

Repair weld requirement: Any repair weld on a P91 joint that has already received PWHT requires full re-PWHT of the entire joint — localized PWHT of only the repair area is not acceptable. This is a firm ASME B31.1 requirement confirmed by real-world failure investigations.

Applicable Standards for P91 Welding

See also: PWHT — Post Weld Heat Treatment: full ASME requirements and Tempilstik® role.

Frequently Asked Questions

The martensite finish temperature (Mf) of P91 is approximately 200°C. If the joint enters the PWHT furnace while still above this temperature, some austenite has not yet transformed to martensite — and PWHT cannot temper austenite. The weld will contain retained unstable austenite after treatment, with mechanical properties below code requirements.

Yes. Part #28327 melts at exactly 392°F (200°C) with a tolerance of ±1% °F / ±3% °C per Tempil® manufacturing standards. It is the part number specified in WPS and QA procedures for P91 and P22 preheat verification on B31.1 and B31.3 projects in Vietnam and internationally.

Not recommended. P91 pipe develops an oxide layer during heating, and the surface emissivity changes with temperature — an infrared gun will produce significantly erroneous readings unless emissivity is continuously adjusted for the changing surface condition. Tempilstik® measures by direct physical contact and is completely unaffected by surface emissivity. Most WPS documents for P91 require or prefer contact-based temperature measurement for preheat verification.

No. P11 (1.25Cr-0.5Mo) requires minimum preheat 150°C (302°F) — use Part #28318. P22 (2.25Cr-1Mo) requires 200°C (392°F) — same as P91, use Part #28327. PWHT for P22 is 680–720°C, lower than P91's 730–760°C. See the preheat temperature reference table for complete material comparisons.

Need Tempilstik® #28327, #28047, or #28065 for P91 projects?

Fast Group Engineering — authorized Tempil® distributor in Vietnam. Direct import from USA, C/O + C/Q + VAT invoice. Individual crayons or box of 10. Stock in HCMC and Vung Tau.

📞 +84 938 888 958  |  ✉ sales@tempil.vn

Related Articles